Infrastructure
Production infrastructure
Section 1
Section 2
Section 3 Section 4
SUU BIE "EMIS Works"
Power supply
Power is supplied from a transformer substation (ТП-414), which disposes of
two transformers with the capacity of 250 kilowatt each. ТП-414 is situated on
the territory of the enterprise. The enterprise also disposes of a built-in
package transformer substation with the capacity of 630 kilowatt.
Heat supply
Heat is supplied from a regional boiler house. The diameter of a supply main
and a reverse main makes up 100mm.
Water supply
Household, drinking and fire-prevention water supply systems with the
diameter of 100 mm are connected to the water supply system of Open Joint Stock
Company "Mogilevpromburvod".No technical water supply system is available.
Sewerage system
Both sewage and storm sewage systems (the former with the diameter of 150 mm
and the latter - 300 mm) are connected to city sewerage system.
SUM RUPE "Ferroconcrete Items Works"
Power supply
Power is supplied from ТП-592, there is a transformer with the capacity of
400 kilowatt and a cell for a second transformer available (no equipment is
available).
Heat supply
Heat is supplied from the boiler house of Closed Joint Stock Company "Mogilev
Silicate Items Factory" with the diameter of 273 mm (heat supply is currently
cut off).
Water supply
United water-pipe network with the diameter of 150 mm is connected to city
water-pipe system.Technical water-pipe network with the diameter of 100 mm is
connected to the technical water pipe network of Closed Joint Stock Company
"Mogilev Silicate Items Factory".
Sewerage system
Sewerage system with the diameter of 200 mm is connected to Mogilevtransmash
Works collector.
Brunch of Republican Unitary Enterprise "Minsk
Automobile Works" "Mogilevtransmash" Works
Power supply
Power is supplied from two transformer substations, which are situated on the
territory of the enterprise, transformers having the capacity of 1600
kilowatt.Heat supplyHeat is supplied from a local boiler house, which is
situated on the territory of the enterprise. It disposes of 5 water heating
boilers with the capacity of 19 Gkal per hour.
Water supply
United household, drinking and fire prevention water-pipe network with the
diameter of 250 mm is connected to city water-pipe systemTechnical water is
supplied from the Dnieper hydraulic works, the diameter of which is 300-400
mm.
Sewerage system
Sewerage effluent (sewerage system having the diameter of 200-300mm) is
drained into city sewage disposal plants. Storm water sewerage effluent
(diameter of sewerage pipe is 500 mm) is drained into the Dnieper river.
Industrial effluent is drained into city sewerage disposal plants after it has
been neutralized.
Gas supply
Gas is supplied from a gas distribution centre, which is situated on the
territory of the enterprise.
Closed Joint Stock Company "Mogilev Silicate Items
Works"
Power supply
Power is supplied from a transformer substation which disposes of two
transformers with the capacity of 1000 kilowatt each. The substation is situated
in the unfinished brick production workshop.
Heat supply
Heat is supplied from enterprise's own boiler house, which is situated on the
territory of the enterprise. The diameter of supply and reverse mains is 273
mm.
Water supply
Water is supplied from an artesian well which is situated on the territory of
the enterprise. The diameter of household, drinking and fire prevention water
pipe systems is 159 mm. Technical water (the diameter of water pipe is 1oo mm)
is supplied from the Dnieper river hydraulic works.
Sewerage system
Both sewage and storm sewage systems (the former with the diameter of 300 mm
and the latter - 400 mm) are connected to "Mogilevtransmash" sewerage
system.
Industrial effluent is drained into "Mogilevtransmash" sewerage system after
neutralization.
Gas supply
Gas is supplied from a gas distribution centre, which is situated in the
boiler house. No outer gas main system is available.
Open Joint Stock Company
"Belremstroysvyaz"
Power supply
Power is supplied from transformer supstation-507, which is situated on the
territory of "Mogielvresursu".
Heat supply
Heat is supplied from a local boiler house, with the diameter of supply and
reverse pipe lines equal to 70mm.
Water supply
United household and drinking water-pipe network with the diameter of 50 mm
is connected to the water pipe line system of Open Joint Stock Company
"Mogilevpromburvod". No technical water pipe line system is available.
Sewerage system
Sewerage system with the diameter of the pipe equal to 200 mm is connected to
city sewerage system. No storm sewerage system is available.
Unoccupied land available for new construction in the
neighborhood of Mogilev-Orsha railway
A united household and drinking water pipeline with the diameter of 500 mm
and a sewerage system collector with the diameter of 400 mm run along this
section.
RUPSE "Zenith"
Power supply
Power is supplied from 7 transformer substations with transformers ranging
from 630 to 1000 kilowatt. All the substations are situated on the territory of
the enterprise.
Heat supply
Heat is supplied from a local boiler house № 1 by the means of pipeline with
the diameter of 270 mm. Heat supply network of the enterprise go through
crawlways.
Water supply
A united household and drinking water system is connected to the city water
supply system. There are 2 water tanks for extra supply of water each holding
500 m3 and a pump station with 2 activating pumps on the site. Technical water
is supplied from Open Joint Stock Company "Mogotex" water supply system. There
are 2 systems of water reuse and local purification systems at the
enterprise.
Sewerage system
Effluent is emptied into the city sewerage system and later transported to
purification plants. Storm effluent is emptied into the city storm sewerage
system.
OJSC "Technopribor"
Power supply
Power is supplied from 2 transformer substations and seven package
substations, situated on the territory of the enterprise with the transformers'
capacity ranging from 630 to 1000 kilowatt.
Heat supply
Heat is supplied from a local boiler house № 1by the means of a pipeline with
the diameter of 320 mm. Heat supply pipeline goes through passes and
crawlways.
Water supply
Household and drinking water is supplied from an artesian well. Water flow
makes up about 10 m3 per hour. Water from the well goes to a tank holding 250
m3. The tank is mainly filled at night. Besides, in case of emergency water is
supplied by means of 2 reserve flumes with the diameter of 250 and 400 mm. The
latter are fitted into the city water main.Technical water is supplied from the
technical water main with the diameter of 150 mm belonging to Open Joint Stock
Company "Mogotex". The diameter of a water pipe on the territory of the plant
makes up 150 mm. Lead-in faces Grishina street.
Sewerage system
Sewerage system consists of pipes with the diameter ranging from 100 to 400
mm. Effluent is purified using purification system of the plant. Storm effluent
drainage is carried out by the means of a collector with the diameter of 800 mm.
It is emptied into the city collector. Sewage effluent is emptied by the means
of a collector with the diameter of 500 mm into the city collector.
Gas supply
Natural gas is supplied to the gas distribution station from city gas network
by the means of a gas pipe line with the diameter of 100 mm under pressure of
5,2-5,3 kg per cm2.
Section 3
Unoccupied land for new construction in the neighborhood of
RepublicanUnitary Plant "Mogilev Automobile Works"
Trunk water pipeline, sewerage and storm sewerage systems, high pressure heat
and gas supplying networks are situated 100-150 m away from the unoccupied land.
Power can be supplied from the transformer substationsituated in the
neighborhood of Lupolovo railway station. A dead-end brunch line can be
built.
Section 4
Unoccupied land for new construction in the neighborhood of Open Joint
Stock Company "Khimvolokno"
When carrying out a new construction project here one can switch to the
following engineering services.
Heat supply
Above-ground pipeline with the diameter of 400 mm.Steam supplySteam may be
supplied by the supply pipe line with the diameter of 133 mm and steam
condensate reversion pipeline.
Water supply
Household and drinking water is supplied by the means of a united circular
water pipeline with the diameter of 300 mm. Technical water may be supplied by
the means of a technical water pipeline with the diameter of 300 mm.
Sewerage system
Sewerage system is made up of a pipeline with the diameter of 300 mm, storm
sewerage system uses a 300-500 mm pipeline.
Gas supply
High pressure gas pipeline with the diameter of 500 mm runs by 3 sections of
unoccupied land. The above named pipeline refers to the city gas system.
Power supply
It is possible to get connected to the following power sources: ПС-110/10,
РП-15, a transformer substation at a sewerage pump station, situated on the
territory of an Open Joint Stock Company "Mogilevkhimvolkno".
|